Link a project¶
Linking a project is a four-step wizard: OpenProject project → Exact project → what to sync → review. Every step is checked before the next one opens, and the first sync starts as soon as you confirm: you land on the project's page and watch it run.
From the Overview page press the setup step, or from Projects press Sync a project. A half-finished wizard can be saved as a draft and resumed later from the Projects page.
Step 1: the OpenProject project¶
When the organization has more than one OpenProject connection, choose the instance first (with one, its name is shown instead). Then search:
- type in the project field, the list filters as you type;
- press Next once a project is highlighted; already-linked projects are greyed out with a linked badge, so a project cannot be linked twice.
The list only contains the projects the token's user is a member of.

Step 2: the Exact project¶
- Administration: the Exact administration (division) the hours go to; only the divisions enabled for OpenProject Sync on the connection are offered.
- Exact project: either Use an existing project (searchable by code or description) or Create a new project: choose a code, the project type (Time and material, Fixed price, Non-billable, Prepaid) and, for a billable type, the customer. Exact refuses a billable project without a customer.
- Hour type: the Exact hour item the lines are booked with. It is optional, but without one no hours are synced.

Step 3: what to sync¶
| Setting | Meaning |
|---|---|
| OpenProject work packages in Exact | three cards: Work packages → activities (every work package becomes a WBS activity, the parent/child structure is kept), Versions → deliverables (versions become WBS deliverables, their work packages the activities) or Hours on the project (no WBS, hours only). Pick the last when the Exact project already has its own work breakdown |
| Only these work package types | when filled, only work packages of these types (e.g. Task, Bug) are synced; press Enter after each type. Empty means all work packages |
| Sync time logged from | the first date on the first run, earlier time entries are not imported. After the first run every run covers the last 45 days, so this date is not a moving floor |
| Time zone | the zone in which a time entry's day is counted when OpenProject and Exact disagree about dates (default: your browser's zone) |
| Exact status as an OpenProject comment | post a comment on the work package when its hours are approved or rejected in Exact. The warning under the switch says exactly what gets written. It stays off when the token's user cannot comment |

Step 4: review¶
Everything in one list: the project and instance, the administration, the Exact project (or the new code and type), the hour type, the WBS mode, the type filter, the date and zone, and the status comments. Press Create and run first sync:

You are taken to the project's page with the first run in progress.
The project's page¶
Each linked project has its own page (Projects → the project name):

- Header: the OpenProject and Exact project as links, the status chip, and the actions Sync now and Pause / Resume.
- Activity: every run with its trigger (scheduled, manual, OpenProject event), when it ran, how long it took and a summary of what it did; runs that mention users without an Exact employee link straight to People.
- WBS hierarchy: the work packages (or versions) and the Exact WBS line each one became, as a tree.
- Conflicts: differences the sync must not decide on its own (an hour line that was already approved in Exact, for example). Each conflict says what OpenProject has and what Exact has; the hours stay where they are until a person acts. See Conflicts.
- Settings: the sync mode (Automatic every … minutes or Manual only), the status-comment switch and a danger zone to Remove link. Removing a link stops the sync; the hours already in Exact stay there.
Pausing and removing¶
- Pause (in the header) keeps the link and its settings; runs are skipped until you resume. Use it for a project that is on hold for a while.
- Remove link (Settings → danger zone) asks for confirmation and deletes the link and its sync state. The draft hour lines and WBS lines that were created in Exact are not touched.